KIPO were appointed by CBRE to provide a detailed visual survey of the Cadent Gas Power station’s MEP services, as well as detailed design of their HV and earthing systems.

Our services and solutions:

  • Undertook a detailed visual survey of MEP services

  • Worked closely with the client to identify budget costs and a programme of works for each project item

  • Provided detailed documents and tender information for RIBA stage 4a deliverables

  • Provided technical support for the duration of the project

  • HV (11Kv) supply and distribution

  • Lighting and Emergency Lighting, earthing and bonding, containment system

  • Switchgear specification

  • Short Circuit Study in accordance with BS EN 60909: 2016, using ERAC’s software

  • Earthing and potential rise calculations in accordance with BS7430

  • Earth fault and Overcurrent grading study and safety settings, using ERAC software

  • Review as to whether inrush protection is needed

PROJECT DETAILS

Client: CBRE

Sector: Power Stations