Projects

 London, UK

City of Westminster College

We were appointed by McLaren Construction Group to perform a review of a non-operational CHP system in order to propose a solution to allow the property to regain use of the scheme.

Our services and solutions included:

  • Came to an agreement with the utility provider to export power to the grid, thereby ensuring the CHP system would continue to function without tripping

  • Modified the design of the 400KVA CHP system with additional BMS controls added to ensure heat rejection was minimised

PROJECT DETAILS

Client: City of Westminster College

Sector: Education

Main Contractor: McLaren Construction Group

City_of_Westminster_College-schmidt_hammer_lassen_architects-photo_010.jpg

London, UK

City of Westminster College

City_of_Westminster_College-schmidt_hammer_lassen_architects-photo_010.jpg
 
 
 

We were appointed by McLaren Construction Group to perform a review of a non-operational CHP system in order to propose a solution to allow the property to regain use of the scheme. Our solution was come to an agreement with the utility provider to export power to the grid, thereby ensuring the CHP system would continue to function without tripping. In addition, KIPO modified the design of the 400KVA CHP system with additional BMS controls added to ensure heat rejection was minimised.


PROJECT DESCRIPTION

Client: City of Westminster College

Main Contractor: McLaren Construction Group

Project: City of Westminster College

Value: £200,000

Sector: Education

Location: London, England