Projects
London, UK
Excel Energy Centre
KIPO was appointed by COFELY to complete the refurbishment of the energy centre that is a part of the Excel. Our experienced engineers also investigated and assessed the best way to achieve a cost effective, long and short term low energy, control and building management system.
Our services and solutions included:
The design of 2 new 2mW CHP engines along with medium and low voltage systems
Negotiation of a 9/8mW export power agreement with SSE and the incoming grid operator
The design of new controls systems including BMS systems and providing new lighting and emergency lighting designs
The result of our recommendations was an energy centre that gave back 9.8 mega watts of power back to the utility grid
PROJECT DETAILS
Client: Cofely Engie
Sector: Energy Centres/ Hotels and Leisure
Main Contractor: Cofely Engie