Projects

London, UK

Excel Energy Centre

KIPO was appointed by COFELY to complete the refurbishment of the energy centre that is a part of the Excel. Our experienced engineers also investigated and assessed the best way to achieve a cost effective, long and short term low energy, control and building management system.

Our services and solutions included:

  • The design of 2 new 2mW CHP engines along with medium and low voltage systems

  • Negotiation of a 9/8mW export power agreement with SSE and the incoming grid operator

  • The design of new controls systems including BMS systems and providing new lighting and emergency lighting designs

  • The result of our recommendations was an energy centre that gave back 9.8 mega watts of power back to the utility grid

PROJECT DETAILS

Client: Cofely Engie

Sector: Energy Centres/ Hotels and Leisure

Main Contractor: Cofely Engie